Bug Tracker Incident #15655

 


Summary
Project
INCDT - xTuple ERP
Incident Category
Bugs
Incident Number
15655
Visibility
public


Product Version
3.8.0Alpha
Fixed In Version
3.8.0Beta2


Summary
*Changing the Schedule date in the Sales Order Screen doesn’t update the linked Purchase Request


Description

Purchase Request Due Date is not being updated on changing the Schedule Date in the Sales Order screen

Steps to Reproduce:
1. Create a Sales Order for an item with ‘Create Purchase Request for a Sales Order’ option enabled in its item site (say TBOX1, WH1 item site)
2. Open the Sales Order in edit mode and change the Schedule date in ‘Header Information’ tab of the Sales Order screen
3. Observe that clicking on Save button doesn’t display ‘Reschedule P/R’ dialog box and the Due date is not updated for the linked Purchase Request


Details
Reporter
vinaysingu
CRM Account
ZenQ
Status
Closed
Assigned
jrogelstad


Priority
Normal
Severity
Minor
Updated
11-22-11 15:16
Resolution
Fixed



Comments

DateUsernameComment
11/22/11 15:16ptyler

Tested okay in 3.8 beta 2 demo db.

10/21/11 21:12svn

Revision: 12691
http://postbooks.svn.sourceforge.net/postbooks/?rev=12691&view=rev
Author: jrogelstad
Date: 2011-10-22 01:12:15 +0000 (Sat, 22 Oct 2011)
Log Message:
-----------
issue #15655: Update P/R when sched. date changes.

Modified Paths:
--------------
xtupleserver/trunk/dbscripts/triggers/coitem.sql

09/30/11 09:19ptyler

Confirmed in 3.8 beta demo db. There's a check for linked WOs but not PRs--and presumably not POs.

09/30/11 01:48vinaysingu

Tested in xTuple version 3.8.0 Beta.
Observed that changing the Scheduled date from the Sales order line item screen successfully updates the Purchase Request Due date.
Changing the Scheduled date from the 'Header information' tab of the Sales order screen updates the scheduled date of the line item but doesn't update the due date of the linked Purchase Request

09/29/11 14:32ptyler

The schedule date is pulled from the SO item screen. Please retest.

09/13/11 08:33vinaysingu

Purchase Request Due Date is not being updated on changing the Schedule Date in the Sales Order screen

Steps to Reproduce:
1. Create a Sales Order for an item with ‘Create Purchase Request for a Sales Order’ option enabled in its item site (say TBOX1, WH1 item site)
2. Open the Sales Order in edit mode and change the Schedule date in ‘Header Information’ tab of the Sales Order screen
3. Observe that clicking on Save button doesn’t display ‘Reschedule P/R’ dialog box and the Due date is not updated for the linked Purchase Request



Characteristics

Backport
No
Operating System
All
Copyright Assigned
Yes
Doc Flag
False

Files

No Files

Related Documents

TypeNumberDescriptionRelationshipRemove
ProjectXTUPLEAPPSPorted From Mantisx


Subscribers

You do not have permission to view subscribers.

No history available